Nasa Artemis I lunar mission’s Space Launch System (SLS) rocket has successfully completed first four Green Run tests for its 212ft-tall core stage.

During Test 4, an initial functional checkout of the main propulsion system components was conducted. It lasted for three weeks and involved the use of gaseous nitrogen and helium.

The test validated the command and control operability, including valve response, timing and more.

Engineers at Nasa’s Stennis Space Centre near Bay St Louis, Mississippi, also carried out leak checks on the core stage-to-facility umbilical fluid and gas connections.

SLS core stage main propulsion system manager Jonathan Looser said: “With test gases flowing through these many parts of a complex rocket stage, we expected the test team to encounter some issues.

“Historically, there’s never been a Nasa human-rated launch vehicle flown without one or more full-up tests before the flight, and they have all encountered first-time issues.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

“As expected, we found a few with valves and seals and addressed them, and now we’re ready to complete the next four Green Run tests.”

The Green Run consists of a series of eight tests and around 30 firsts, including first propellant tanks loading, first flow through the propellant feed systems, the firing of all four engines for the first time, and more.

Engineers will move to the Green Run Test 5, where the stage thrust vector control system will be checked.

Nasa’s Artemis 1 is the first in a series of missions to enable human exploration to the Moon and Mars.

Last month, Nasa announced that the Mars 2020 Perseverance rover cleared its flight readiness review, marking a key milestone in preparation to its launch.