Madrid Barajas International Airport (MAD/LEMD), Spain

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
Completion Date
2004
Project Cost
€2.91bn
Masterplan and Design Development
Black & Veatch
New Terminal Design and Architecture
Richard Rogers Partnership, Estudio Antonio Lamella, TPS (Carillion), Inetec
New Terminal Construction
Joint venture of FCC, ACS, Ferrovial, Necso and Sacyr
APM Study
Lea+Elliott
Baggage Handling System
Siemens Dematic AG, FKI Logistex Crisplant a/s

Passenger growth of 10% per annum at Madrid Barajas International Airport has led the Spanish airport authority (AENA) to approve a €2.91bn expansion that includes the construction of a new terminal and satellite building, a new baggage handling system and an automatic people mover.

The expansion also featured numerous other projects including new parking facilities and a highway extension. Eurocontrol, the European organisation for the safety of air navigation, projects that Madrid Barajas Airport will become Europe's third busiest airport by the end of 2012.

MADRID BARAJAS AIRPORT TRAFFIC

In 2000, more than 141 million passengers were serviced at Spanish airports, and passenger numbers in Spain grew 9% more than the EU average. Madrid Barajas Airport saw yearly passenger growth of 10%, a total of 35 million passengers, and accounted for 27% of air traffic between the EU and South America.

The airport handled the most cargo traffic in Spain, and in terms of cargo volumes represented the eighth busiest airport in Europe and the 31st internationally.

Terminals 1, 2 and 3 are adjacent terminals that are home to SkyTeam and Star Alliance airlines, as well as Air Europa. The new Terminal 4 is home to Iberia Airlines, its franchise Air Nostrum and all Oneworld partner airlines.

NEW TERMINAL BUILDING

Since the early 1990s plans have been underway for the construction of a new terminal building. This culminated in an international design competition which was won by a team comprised of British architect Richard Rogers, Spanish Estudio Antonio Lamella, the structural consultant TPS (Carillion) and Inetec (structurally complete by December 2005).

In February 2006 Terminal 4 was inaugurated by the Prime Minister of Spain, Jose Luis Rodriguez Zapatero. This new terminal makes Barajas the world's largest airport in terms of terminal area, with an area of more than one million square metres (11 million square feet).

The facility consists of a main building (T4) (470,261m²) and satellite building (T4S), which are separated by approximately 2.5km; the new terminal was designed to allow passengers an altogether stress-free start to their journey.

The terminal incorporates impressive illumination, augmented by glass panes instead of walls and numerous dome structures in the roof which allow natural light to pass through. With the new T4 facility Barajas is now designed to handle 70 million passengers annually.

"Madrid Barajas International Airport handles the most cargo traffic in Spain."

The 1km-long wing-shaped building was designed with a wide range of environmentally friendly, energy consumption-reducing installations such as efficient cooling systems, extensive shading to the façades and roof lights and zonal lighting. It hosts 174 check-in desks, 26 security controls, 20 baggage conveyors, 38 boarding gates, 28 movable ramps, 76 elevators and 22 escalators.

SATELLITE BUILDING

The new satellite building will have a total floor surface of 287,384m² and will be capable of handling around 15 million passengers a year with 26 gates. The building will consist of two blocks, one that will host the arrival and departure facilities for passengers and the other for passport facilities and commercial zones. In addition to that, the satellite building will provide parking spaces for up to 9,000 cars.

AUTOMATIC PEOPLE MOVER

An Automatic People Mover (APM) will connect the new terminal building to the satellite building. Automatically guided vehicles will transport passengers between two stations in a tunnel, with two platforms in the principal terminal and one in the satellite building.

The APM will cover a distance of 2,100m and run 24 hours a day. Six trains will transport a maximum of 13,000 passengers an hour at a maximum speed of 60km/h. The transfer between stations will take around three minutes with trains stopping in two-minute intervals.

AUTOMATIC BAGGAGE HANDLING SYSTEM

The new terminal will host an automatic baggage handling system, capable of handling up to 16,500 pieces of luggage an hour on a total of around 78km of conveyor belt. The system will process baggage from arrivals, departures and transit flights within the new terminal and the satellite building.

Siemens Dematic AG is undertaking construction of the baggage handling system. Design and engineering services were supplied by FKI Logistex Crisplant a/s. The company subsequently received an order to design, manufacture and install four S-3000M Tilt-Tray sorters, 172 check-in systems and an empty tote system.

"The aircraft contol tower, which was first built and commissioned in 1998, has been fully refurbished."

OTHER DEVELOPMENTS

The aircraft contol tower, which was first built and commissioned in 1998, was fully refurbished during the course of the expansion project.

Work included equipment update and software renewal as well as the expansion of the parking facilities and the air traffic navigation offices. The work has not altered the physical appearance of the tower. The 840m underground section of the M11 highway linking Barajas to Paracuellos del Jarama has also been expanded.

LEAD CONTRACTORS

The masterplan for the expansion of Madrid Barajas Airport, as well as design development, was undertaken by Black & Veatch. British architect Richard Rogers teamed up with Spanish firm Estudio Antonio Lamella for the project bringing in UK structural consultant TPS (Carillion) and Spanish firm Inetec, the latter having the legal powers to sign off the drawings. The terminal building construction is undertaken by a joint venture of FCC, ACS, Ferrovial, Necso and Sacyr.

An order worth €28.9m for baggage handling equipment went to FKI Logistex Crisplant a/s. Main contractor for the construction of the parking facilities is Spanish company Dragados. Lea+Elliott performed various services during the planning phases of the APM including a feasibility study and cost estimates.

The project management was the remit of Parsons Brinkerhoff (PB). PB's scope of services included design review, construction support, project controls and technical audits. The technical audits of individual projects recommended to the client where improvements could be made in all aspects of project management.

In addition, the firm assisted in the tender evaluation process for the terminal building ($600m construction value), satellite ($300m construction value), and parking structure ($140m construction value).

RUNWAY CONSTRUCTION

During the construction of Terminal 4, two more runways (15L/33R and 18L/36R) were also constructed to aid in the flow of air traffic arriving and departing from Barajas. These runways were officially inaugurated in February 2006 (together with the terminals), but had already been used on several occasions beforehand to test flight and air traffic manoeuvres.

"One take-off or landing every 30 seconds is now possible."

Barajas now has four runways: two on a north–south axis and parallel to each other (separated by 1.8km) and two on a northwest-southeast axis (and separated by 2.5km). This allows simultaneous take-offs and landings into the airport, allowing 120 operations an hour (one take-off or landing every 30 seconds).

METRO SERVICES AND RAIL SERVICES TO T4

The Metro Line 8 runs directly to Terminal 2; from this terminal there is a free connecting bus to Terminal 4 and from Barajas town metro station to Terminal 4. The Line 8 extension to T4 is still under construction and will be completed early in 2007.

In October 2006 the construction of a Cercanias link between Chamartin train station and Terminal 4 was started. When this project is finished in 2009 a single Cercanias Line will link Madrid Barajas Terminal 4 with Chamartin and Atocha AVE high-speed train stations.



Expand Image Expand Image
Madrid Barajas airport has embarked on a €2.91bn expansion programme.



Expand Image Expand Image
The new terminal building will have an annual capacity of 35 million passengers.



Expand Image Expand Image
The wing-shaped building will have a total floor area of over 470,000m² and is designed with a wide range of environmentally friendly, energy consumption reducing installations.



Expand Image Expand Image
The new satellite building will be capable of handling an additional 15 million passengers a year.



Expand Image Expand Image
The new terminal will host an automatic baggage handling system, capable of handling up to 16,500 pieces of luggage an hour.



Expand Image Expand Image
The interior length of the new terminal at Madrid Barajas International seems to go on forever.



Expand Image Expand Image
The innovative wave style structure of the roof of Madrid Barajas's new terminal building.



Expand Image Expand Image
The terminal roof has glass domes to let in natural light.



Expand Image Expand Image
With the new T4 facility Barajas is now designed to handle 70 million passengers annually.



Expand Image Expand Image
The Madrid Barajas new terminal has an automatic baggage handling system capable of handling up to 16,500 pieces of luggage an hour.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  

Suppliers
FB TechnologyJacob's ConsultancyTerma

Newsletter Sign-Up
For all the latest news in the airport industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Special Reports
White Papers
Jobs & Careers
Industry News
Gallery
Events & Exhibitions
Newsletter Archive
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the airport industry