Western Sydney International (Nancy-Bird Walton) Airport in Australia has completed the construction of a new bridge as part of its initial earthworks.

The project is part of the first phase of the new airport’s construction.

It included the realignment of a 1.6km-long section of Badgerys Creek Road, the construction of a shared footpath for cyclists and pedestrians, and a new intersection at Elizabeth Drive.

Western Sydney Airport CEO Graham Millett said: “Technically we’ve built two bridges, one north bound and one south bound, both 39m long and with a combined width of 49m, around the same width as Sydney’s Harbour Bridge.

“Constructing the bridge was no mean feat; it’s built on 21 mammoth 45t girders manufactured with almost 900t of concrete. Around 20,000t of asphalt have been laid along the new road, along with 116 new street lights being installed.

“As with most road works, there have been traffic changes for motorists and we thank them for their ongoing patience while this work takes place.”

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Of the entire 1,780ha airport site, initial earthworks constitute about 6% and include the movement of 1.8 million cubic metres of earth.

The project’s major earthworks are expected to start early this year, resulting in the movement of over 23 million cubic metres of earth for the terminal and runway.

The A$5.3bn ($3.5bn) airport will open in 2026 and will be equipped to handle ten million passengers annually.

Last November, Western Sydney Airport selected Aurecon to provide terminal precinct engineering design services, while Cox Architecture and Zaha Hadid Architects (ZHA) were appointed to design the airport’s terminal building.