Key Data:
Project Type
New international airport
Estimated Investment
$585m
Construction Started
2006 (first phase), there will be three phases
Key Players:
Sponsors
Corporacion Quiport SA (Quiport), Aecon, Andrade Gutierrez Concessoes of Brazil, the Airport Development Corporation of Toronto and HAS Development Corporation of Texas, City of Quito,
Corporacion Aeropuerto y Zona Franca del Distrito Metropolitano de Quito (CORPAQ)
Lead Contractors, Designers, Architects and Engineers
Marshall Macklin and Monaghan, Avatar Consulting, and the Canadian Commercial Corporation (CCC), Aecon, Andrade Gutierrez Constructores, Volecam, Equitrans
Financing
Corporacion Aeropuerto y Zona Franca del Distrito Metropolitano de Quito (CORPAQ), Overseas Private Investment Corporation,
Export-Import Bank of the USA, Inter American Development Bank and Canada's Export Development Corporation (EDC)
Passengers (Estimated)
4.5 million in 2010, 5.5 million in 2020, 7.5 million in 2030