Key Data:
Order year
1997 (Terminal Master Plan)
Construction started
2002 (I-70); 2003 ATCT and terminal
Project type
Major expansion: new terminal, air traffic control tower, access roads, parking, etc.
Location
Indianapolis, Indiana, USA
Estimated investment
$1 billion
Completion
2004 (I-70); 2006 (ATCT); opening (terminal) due on 28 October 2008
Key Players:
Sponsors
Indianapolis Airport Authority (IAA)
Lead contractors, designers, architects and engineers
HOK (master designer); Hunt Construction Group and Turner Construction Company (primary construction managers); Smoot Construction, Trotter Construction Company, G.M. Construction, Powers & Sons Construction Company, Harmon Construction, Inc.,
Shiel Sexton (construction); Syska & Hennessey and Thornton-Tomasetti Engineers (mechanical and structural engineering); BSA Life Structures and Blackburn Architects (owner's technical representatives);
Hanscomb (cost estimating); Leigh Fisher Associates (financial planning); Gibson and Associates (business outreach / diversity program coordinator); Executive Media (communications); Teng & Associates Inc (ATCT architect)
Traffic:
Passengers
7.4 million (2003)
Cargo
980,694t of cargo and mail (2003)
Flights
279 departures daily (2003), 204,059 landings / take-offs (2003)