Key Data:
Project Type
Airport Expansion
Location
Miami, Florida, USA
Estimated Investment
$5,917 million (overall cost)
Key Players:
Sponsor
Miami Dade County Aviation Department
Architects and Designers
General: Perez and Perez, MGE Architects, Borelli and Associates (main architects), Mateu Carreno Rizo and Partners, Rodriguez and Quiroga Architects Chartered, Runway: Edwards and Kelcey, Engineerin
Contractors
General: Parsons Odebrecht, Crompton Construction, TGSV Enterprises Inc, Aventura Engineering and Construction, Carivon Construction, Dodec Inc, Greenbriar Construction, Gavarette Construction Co, Gra
Traffic:
Passengers
40 million per annum, south terminal 8.1 million per annum
Airline Movements
534,775 per annum