Cleveland Hopkins International Airport

Cleveland Hopkins International Airport (CLE/KCLE), OH, USA

Cleveland Hopkins International Airport is in the midst of an ongoing $1.5bn expansion and renovation program. Back in 1997, the airport realised it had to increase capacity to meet growing travel demand.

"The new runway at Cleveland Hopkins International Airport is 1.3 miles long and allows up to ten more takeoffs and landings an hour."

The airport, owned by the City of Cleveland, is a hub for Continental Airlines and passenger numbers in 2002 reached close to 11 million (passenger numbers have fallen since the peak of 13.8 million in 2000 due to the terrorist attacks (10.4 million passengers in 2004), but numbers are now beginning to increase), with 58% of these being Continental business and leisure travellers. International destinations include Canada, the Caribbean, Mexico, Puerto Rico and London.

A masterplan was formulated, based around the most important requirement – a new parallel runway that could facilitate electronically aided simultaneous take off and landing operations. This runway, 6L-24R, became operational in early 2004.

As well as a new runway, the masterplan has also included improvements to the terminal, parking garages and roadways. A new de-icing facility and a maintenance centre were also commissioned in 2002.

PLANNING THE AIRPORT EXPANSION

A major problem faced by the Program Management Team (PMT) – a joint venture partnership headed up by Parsons Transportation Group, a US-wide construction company – concerned the location of the airport.

Cleveland Hopkins Airport is surrounded on all sides by the Rocky River Reservation Park and gorge to the south and west, Highway I-480 and State Route 17 to the north, NASA Glen Rocket Engine Test Facility (RETF) to the west, and State Route 237 and Ford Motor Engine and Assembly Plant to the east. Expansion outside the airport boundaries was therefore not an option.

Over 20 projects were identified to overcome the many obstacles facing the construction of the new runway in the existing area, including the relocation of some NASA buildings and several surrounding businesses in Brookpark Road. Many roads surrounding the airport also required either rerouting or upgrading to allow for the new runway and also to handle the proposed increased passenger traffic. The entire project is scheduled for completion by early 2007.

Over $60m was invested to protect the valuable natural habitats around the airport. When construction was completed, more than 350ac of wetlands and 30,000ft of streams had been preserved.

"Over $60m was invested to protect the valuable natural habitats around the airport. "

FUNDING

Funding of the $1.5bn project has come from many sources, including the City of Cleveland, (Federal, State, local and user communities - involving a federally backed $149m letter of intent), general aviation revenue bonds, passenger facility charges and airline-supported rates and charges.

NEW RUNWAY 6L-24R

The new runway at Cleveland Hopkins is 1.3 miles long and allows up to ten more takeoffs and landings an hour. By early 2007 the runway will have been extended a further 2,000ft (phase two) to 11,225ft allowing its use for wide-bodied planes and larger aircraft such as the A380 as well as aircraft carrying a higher fuel load.

With the addition of a new radar TRACON facility, the airport's overall capacity will be set to increase from its present 80 takeoffs and landings per hour to approximately 120 when required by operation capacity requirements.

The new runway also facilitates quicker takeoffs and landings, limiting the waiting time for planes both on the ground and circling in the air. This helps reduce delays to passengers and airline costs.

The runway environment has also become safer, by reducing the need for planes to taxi and manoeuvre across runways. It is hoped that this increased capacity will also attract more budget carriers. The 6L-24R extension to the south has eliminated the need for incursion onto the crosswind runway 10-28 during airfield operations, which has greatly increased safety. Following the extension of runway 6R-24L the parallel runway to the south will also no longer need to interact with the crosswind runway.

The contractor for the construction of the runway is Anthony Allega Cement Contractor Inc, Valley View, Ohio. Allega Concrete chose to construct cement plants at the airport – substantiated by the fact that in order to enable a continuous pour across the runway area 6,000yd³ of concrete would be needed (the equivalent of 700 cement trucks). The contract for this part of the project is estimated to be $130m.

"Several new parking facilities were constructed as part of the airport upgrade."

Doan Pyramid Electric won the contract to install the electrics for the new runway. This amounted to 1.9 million feet of No. 85kV field cable, 160,000ft of 500 MCM 15kV feeder cable, 68,000ft of No. 1/0 5kV power cable and 60,000ft of fibreoptic cable. The primary power supply was redistributed from steel towers to separate concrete-encased underground duct banks and a new electrical vault and 138kV substation was constructed.

RUNWAY SAFETY SYSTEMS

The new runway is classified category III (CAT III), which allows pilots to use it in very low visibility. The FAA is installing the navigational instrumentation, which is to be commissioned by 25 November 2006. At that point, the new runway will be fully commissioned as a CAT III runway. Additional instrumentation has also been installed that will allow Simultaneous Offset Instrument Approach (SOIA) landing and ground control, thus completing the full capacity increase needed by operations.

SOIA instrumentation uses a state-of-the-art radar precision runway monitoring system, of which fewer than 12 are currently in use in the country. In addition, a surface movement guidance control system has been installed to enable surface traffic to navigate to and from the terminal in low visibility.

Finally, a state-of-the-art computerised control and monitoring system has upgraded existing and new runway lighting control. All of this work was completed and in operation by February 2005.

PARKING FACILITY, PEDESTRIAN CONCOURSE BRIDGE AND CAR RENTAL FACILITY

Several new parking facilities were constructed as part of the airport upgrade. One consisted of the construction of new 2,400-space and 1,400-space parking structures, totaling 1,168,000ft², as well as a new passenger bridge. The architect for this project was URS Greiner & Desman and the general contractor was Donley Inc, of Cleveland, Ohio. This project was completed in 2003.

"The masterplan also included improvements to the terminal, parking garages and roadways."

Donley Inc was also responsible for a new 17,440ft² consolidated rental car centre that houses eight rental car companies and 1,250 cars. This was designed by VS Architects Inc and was an aggressive fast-track project completed in less than six months. Lighting for this facility was provided by The V Group, Cleveland, Ohio, who used Gullwing lights which allow for maximum light levels using a minimal number of poles.

Another new 1,500-space covered parking lot – the airport fast park – was constructed by DAS Construction Co, at a cost of $10m. DAS also performed demolition of existing parking and site infrastructure, site development of the parcel, a 3,600ft² operations and maintenance building, and the design-build-construction of a 436,000ft² covered parking structure. $2m of the $10m project was spent removing chemicals from the property. Half & Associates, of Dallas, was the project coordinator.

TERMINAL EXPANSIONS

An expansion project allowing for the design and construction of a 27,200ft² baggage claim area on the northeast end of the existing terminal building was recently completed.

Other projects include improvements to concourse connectors and mall areas, with 24 added specialty shops and restaurants and new signage in and around the airport. A new visitor information centre is located on the baggage claim level.

PROPOSALS FOR A FURTHER RUNWAY

The completion of runway 6L-24R is just one milestone in the five-year expansion project. The project has already involved a major land swap between the cities of Cleveland and Brook Park. NASA Glenn became part of Brook Park in exchange for the IX Center (expo centre), which will be torn down in preparation for a further runway that city officials believe will be needed by 2014.

"A new visitor information centre is located on the baggage claim level."

To make way for this proposed runway, 468 homes in Brook Park will be purchased by Cleveland and demolished over the next 11 years (this is highly controversial and there have been a number of lawsuits over compensation, currently the airport has set aside $75m for purchase of property outside the airport confines for expansion activity).

Other suburbs surrounding the landlocked airport are receiving financial assistance to insulate about 13,000 homes against the noise from more frequent flights.

Printable Version Click here for printable version



Expand Image
Map of the airfield showing new runway and expansions.
Map of the airfield showing new runway and expansions.
Expand Image
Views of the completed runway.
Views of the completed runway.
Expand Image
Relocation of NASA liquid hydrogen transfer.
Relocation of NASA liquid hydrogen transfer.
Expand Image
Relocation of NASA rocket testing facility.
Relocation of NASA rocket testing facility.
Expand Image
Sketches of new baggage claim extension.
Sketches of new baggage claim extension.
Expand Image
New car rental facility.
New car rental facility.
Expand Image
Gullwing lights used at the new rental facility.
Gullwing lights used at the new rental facility.
FEATURED SUPPLIERS



client logon
Home
New On This Site
Products & Services
Company A-Z
Special Reports
White Papers
Jobs & Careers
Industry News
Advertise With Us
Events & Exhibitions
Newsletter
About Us
Atom FeedRSS Feed
What is RSS?